BP/BG can handle tasks with missing start date or end date

    XMLWordPrintable

Details

    • Epic
    • Status: In Progress (View Workflow)
    • Critical
    • Resolution: Unresolved
    • None
    • None
    • None
    • Business
    • Tasks with no dates
    • Scheduling
    • BigPicture, BigGantt
    • JIRA server, JIRA cloud
    • 174
    • 174
    • Show
      Confluence https://wiki.softwareplant.com/display/DOC/Tasks+without+dates
    • $i18n.getText("admin.common.words.hide")
      $i18n.getText("admin.common.words.show")
      var cfToHide1 = document.getElementById("rowForcustomfield_18501"); if(cfToHide1){cfToHide1.style.display="none";} var cfToHide2 = document.getElementById("rowForcustomfield_18502"); if(cfToHide2){cfToHide2.style.display="none";} var cfToHide3 = document.getElementById("rowForcustomfield_19700"); if(cfToHide3){cfToHide3.style.display="none";} var cfToHide4 = document.getElementById("rowForcustomfield_18400"); if(cfToHide4){cfToHide4.style.display="none";}

    Description

      Before change:

      When task is added to app, its dates are set automatically to a default value (today).

      After change:

      When task is added to app it can stay without dates and have them added only when the user explicitly sets them.

      At any time, the user will be able to remove one or both of the dates from the task (and add them again at any time).

       

      Reason of change:

      For many customers, a task without dates is seen as an unplanned task. The operation of setting default dates on a task by BP is often perceived by customers as undesirable behavior.

      If BP automatically sets the dates, the client does not know if the task was scheduled by him or if the dates were entered by BP, which breaks his internal process.

      Attachments

        Issue Links

          People

            marcin.orkiszewski Marcin Orkiszewski
            marek.lewandowski@appfire.com Marek Lewandowski (Inactive)
            Adrianna Pisarska Adrianna Pisarska
            monika.cecot Monika Cecot , mateusz.maniak Mateusz Maniak , michal.piaskowski Michał Piaskowski , paulina.binek Paulina Binek , anna.cieplota Anna Ciepłota , aneta.wojcik Aneta Wójcik , patryk.pesta Patryk Pesta , patryk.watras Patryk Watras , patryk.krasuski Patryk Krasuski , maciej.glownia Maciej Głownia , kamil.koszarny Kamil Koszarny , karolina.chrzanowska Karolina Chrzanowska , adrianna.pisarska Adrianna Pisarska , laura.urbanowicz Laura Urbanowicz , rafal.staskiewicz Rafał Staśkiewicz , marcin.koman Marcin Koman , grzegorz.figlarz Grzegorz Figlarz , magdalena.dereszewska Magdalena Dereszewska , rafal.leoniak Rafał Leoniak (Inactive) , marta.kucharska Marta Pastor (Kucharska) , marcin.orkiszewski Marcin Orkiszewski , mateusz.rusinski Mateusz Rusiński , mateusz.filipek Mateusz Filipek (Inactive) , monika.bialucha Monika Białucha , piotr.rozdeba Piotr Rozdeba , tomasz.jaskiewicz Tomasz Jaśkiewicz , pawel.nowicki Paweł Nowicki , ewelina.cedro Ewelina Cedro , maciej.bartylak Maciej Bartylak (Inactive) , piotr.zygmuntowicz Piotr Zygmuntowicz (Inactive) , adam.biedruna Adam Biedruna , alexey.chekel Alexey Chekel (Inactive) , marta.mazurkiewicz Marta Mazurkiewicz (Inactive) , anna.kicior Anna Kicior (Inactive) , michal.mrozowski Michal Mrozowski , vira.yaremchuk Vira Yaremchuk , grzegorz.duzy Grzegorz Duży , piotr.polanski Piotr Polański , mateusz.wyzinski Mateusz Wyzinski , pawel.guz Pawel Guz , marta.rozewska Marta Różewska (Inactive) , michal.niwinski Michal Niwinski (Inactive) , jerzy.sekula Jerzy Sekula
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated: